Check In and Out at Work in construction from 1 April 2027

From 1/4/2027, Check In and Out at Work of the National Social Security Office (RSZ/ONSS) also applies to work on immovable property (except cleaning) and the delivery of ready-mixed concrete, on sites with a total amount of at least €500,000 excluding VAT. Anyone working on such a site registers the start and end of their activity themselves, in real time and at the workplace, for example with the QR code of the declaration of works. Until then, Checkinatwork applies: registering attendance before someone starts work. This is a separate RSZ obligation: Klox has no link with it.

Written by Robin Verbelen, founder of Klox

Updated on 17/10/2026Last checked on 10/10/2026

Today: Checkinatwork

For work on immovable property, except maintenance and cleaning, registration in Checkinatwork is already mandatory today from a total amount of €500,000 excluding VAT (for works started after 29/02/2016). That threshold can be reached at the start or during the works.[4]

  • Attendance is registered before the person starts work. A registration can be changed or cancelled until the end of the day it relates to.[4]
  • The declaring contractor informs everyone involved, for example with a poster with a QR code, and remains responsible for its chain of subcontractors.[4]
  • Registration is possible through, among other things, a registration device compatible with the device on the site or through the Checkinatwork online service.[4]

From 1/4/2027: Check In and Out at Work

Check In and Out at Work is the RSZ online service for registering attendance at work: "in" at the start, "out" at the end of the activity. For certain cleaning activities it has been mandatory since 01/09/2024. From 01/04/2027, work on immovable property (except cleaning) and the delivery of ready-mixed concrete are added, if the total amount excluding VAT is €500,000 or more. The legal basis is the programme law (programmawet) of 30/05/2026, title 6, chapter 1, articles 124 to 131.[1]

Checkinatwork today and Check In and Out at Work from 01/04/2027, for work on immovable property
Checkinatwork (today)Check In and Out at Work (from 01/04/2027)
Threshold€500,000 excl. VAT[4]€500,000 excl. VAT, also for ready-mixed concrete[1]
WhatAttendance, before the person starts workStart and end of the activity[1]
Who registersBefore the start, also in advance by the employer or contractor based on the schedule; can be changed until the end of the day[4][5]The person themselves, in real time at the workplace; the employer does not register in advance on their behalf[2]
Checkinatwork today and Check In and Out at Work from 01/04/2027, for work on immovable property

Who registers: employees, self-employed people, temporary agency workers and trainees.[1] Employers, contractors and companies with a contract with a client make sure their employees, subcontractors and the employees of those subcontractors are registered.[3] According to an analysis by Van Havermaet on Lexgo, this also applies to foreign employers and their subcontractors working in Belgium, and Check In and Out at Work thereby replaces Checkinatwork on those sites.[5]

How to register: QR code, URL or your own system

The RSZ describes these channels:[2]

  • Smartphone. The declaration of works generates a QR code or a specific URL for the attendance registration of your workers. Without a QR code or URL it is also possible, with the number of the declaration of works.
  • Web service. Registration through a badge, track and trace or another application: an existing system communicates with the RSZ web service.

As an employer you may not register on behalf of your people, but you must provide the means to register. You may combine channels.[2]

So a QR code is allowed, but it has to be the one from the declaration of works with the RSZ. Any other QR code on the site, including the Klox one, is not a registration in Check In and Out at Work.

Check In and Out at Work is not working time registration

Check In and Out at Work records who is present on which site and when, with the RSZ. Your own working time registration, with breaks, corrections, overtime and an export for your social secretariat or the inspectorate, is something else. An employee who works on two sites in one day or drives to the warehouse in between has several RSZ registrations but one working day.

What each registration does
Check In and Out at Work (RSZ)Klox
PurposeAttendance at a workplace, declared to the RSZWorking time per employee for your own register
WherePer site with a declaration of worksPer worksite, and a construction site can be a worksite
HowQR code or URL of the declaration of works, or a system through the RSZ web serviceBrowser, QR code of the worksite in Klox, or the Klox Kiosk with NFC badge
Breaks, corrections, exportNot the purposeBreaks, corrections with reason and author, export as PDF and CSV
LinkThe RSZ's own serviceNo link with Checkinatwork or Check In and Out at Work
What each registration does

What the rule says

From 01/04/2027, anyone working on a site of €500,000 or more registers the start and end themselves, in real time, in Check In and Out at Work.[1]

What Klox does

Klox registers working time per worksite, including a construction site, with the QR code of that worksite or at the Klox Kiosk. Klox does not register anything with the RSZ and has no link with Checkinatwork or Check In and Out at Work. You do that registration separately, through the RSZ channels.

Example: a day on site after 01/04/2027

A fictional contractor from Mechelen is renovating a school building for €1.2 million excluding VAT. On Tuesday 06/04/2027, four of its own employees and two people from a subcontractor are working there.

Fictional day on site, 06/04/2027
MomentCheck In and Out at WorkWorking time (e.g. in Klox)
07:15Everyone scans the QR code of the declaration of works on arrivalThe company's own employees clock in at the worksite "School site"
12:00 to 12:30Register break in and outBreak started and stopped
14:00One employee checks out and drives to another site, where he checks in againHis working day continues
16:00Everyone checks out on leavingClock out; the daily register follows automatically
Fictional day on site, 06/04/2027

The contractor makes sure the subcontractor's people are also registered in Check In and Out at Work. Their working time is registered by their own employer, the subcontractor.[3]

And the general registration obligation?

Check In and Out at Work is separate from the announced general obligation to register the working time of every employee. That is not law yet. The current status, with sources, is on time registration mandatory in 2027?

Frequently asked questions

From when does Check In and Out at Work apply in construction?
From 01/04/2027, for work on immovable property (except cleaning) and the delivery of ready-mixed concrete, if the total amount excluding VAT is €500,000 or more (according to the RSZ). For certain cleaning activities it has applied since 01/09/2024.
What has to be registered?
The start and end of the activity at the workplace, by the person themselves and in real time. According to the general explanation of the RSZ, rest breaks as well.
Can an employee check in with a QR code?
Yes. The declaration of works generates a QR code or a specific URL for the attendance registration. A badge or other system through the RSZ web service is also possible. The employer must provide the means to register, but may not register on behalf of the employee.
What continues to apply until 01/04/2027?
Checkinatwork: for work on immovable property of €500,000 or more excluding VAT, you register attendance before the person starts work. That registration can be changed until the end of the day.
Does Klox register my people in Check In and Out at Work?
No. Klox has no link with Checkinatwork or Check In and Out at Work. Klox registers working time per worksite, including per construction site, with a QR code or the Klox Kiosk. You do the registration with the RSZ separately.

Sources

  1. [1]Check In and Out at Work (in Dutch), National Social Security Office (RSZ/ONSS), accessed on 10/10/2026
  2. [2]Check In and Out at Work: how do you register attendance? (in Dutch), National Social Security Office (RSZ/ONSS), accessed on 10/10/2026
  3. [3]Check In and Out at Work: who is it for? (in Dutch), National Social Security Office (RSZ/ONSS), accessed on 10/10/2026
  4. [4]Checkinatwork: work on immovable property (in Dutch), National Social Security Office (RSZ/ONSS), accessed on 10/10/2026
  5. [5]Active on Belgian construction sites? Checking in and out becomes mandatory from 2027 (Van Havermaet, 24/08/2026) (in Dutch), Lexgo, accessed on 10/10/2026
  6. [6]Towards mandatory check-in and check-out in construction from 2027 (11/03/2026) (in Dutch), Securex Lex4You, accessed on 10/10/2026